QCLNG Project 2013-2015

Project Summary

  • Client Thiess Pty Ltd
  • Location QLD
  • Date Commenced On-Site July 2013
Client

Thiess Pty Ltd

Date IES Commenced On-Site

July 2013

Incidents
Defects
Location

QLD

The Queensland Curtis LNG (QCLNG) project was the World’s first to convert coal seam gas to LNG. Thiess was the tier 1 contractor for the $2.1 billion construction of 17 field compression stations (FCS) and 4 central compression plants (CPP) in the Surat Basin. IES was engaged under a subcontract agreement to provide a self sufficient team of engineers, supervision and trades for numerous structural steel and pipe installation packages.

IES delivered the construction to client approved specifications primarily AS4100 “Steel Structures” and AS3990 “Mechanical Equipment – Steelwork”; for fabrication and erection of structural steel, and ASME16.5 “Pipe Flanges” and ASME B31.3 “Process Piping”, AS4041 “Pressure Piping” and AS2885 “Pipelines – Gas & Liquid Petroleum”, for the stock control, installation, welding and testing of the pipe work installations.

There was also a requirement for non destructive examination (NDE) of pipe welds in accordance with ASME V , hydro testing to AS4041 and nitrogen leak testing to ASME B31.3 for joint seal integrity. IES was heavily integrated into this process providing supervision, engineering inspection & sign off.

Key Milestones

July 2013 – IES commenced at Ruby Jo CPP.

August 2013 – Thiess identified the need for a night shift crew. IES was a ’go to’ choice and operated successfully with a peak crew size in excess of 120 personnel, taking the lead on night shift roster.

December 2013 – Ruby Jo CPP achieved MC with IES providing a notable contribution towards achieving this goal. Following the successful operation of a night shift crew at Ruby Jo, the IES contract was extended to include Bellevue CPP and subsequently Jordan CPP.

July 2014– Bellevue CPP achieved MC.

November 2014—Jordan CPP achieved MC.

Project Summary

  • Client Thiess Pty Ltd
  • Location QLD
  • Date Commenced On-Site July 2013
Client

Thiess Pty Ltd

Date IES Commenced On-Site

July 2013

Incidents
Defects
Location

QLD